作業規程目錄
第一章 工程概況............................. .............................................................................(2)
第一節 巷道布置..........................................................................................................(7)
第二節 工期要求.................................................................... .....................................(8)
巷道用途……………………...........................................................................(9)
服務年限……………………...........................................................................(9)
工程量……………………..............................................................................(9)
工程結構特點……………………...................................................................(9)
巷道標高……………………...........................................................................(9)
地質情況概述............................ .....................................................................(4)
第一節 地質綜合柱狀圖..............................................................................................(7)
第二節 地質預想剖麵圖..............................................................................................(8)
第三節 頂底板岩性描述…………………..................................................................(9)
第四節 煤層賦存條件………………………………………………………………..(9)
第三章 巷道支護說明書..............................................................................................(7)
第一節 巷道壓力情況及支護選型..............................................................................(7)
第二節 巷道支護及各種管線設備布置圖............................. ...................................(8)
第三節 巷道特征及每米巷道消耗表.........................................................................(9)
第四章 施工方法及勞動組織.....................................................................................(10)
第一節 施工方法.........................................................................................................(10)
第二節 爆破說明書.............................................................................................. ......(11)
第三節 勞動組織圖表........................................................................................ ........(13)
第四節 作業循環圖表................................ ................... .............................................(13)
第五節 主要技術經濟指標............................................. ........................................ ...(14)
第五章 局部通風機係統設計.................................................................................... (15)
第一節 局部通風係統............................................. ......................................... .........(15)
第二節 局部通風設計............................................. ......................................... .........(16)
第六章 機電運輸係統及管理.................................................................................... (19)
第一節 供電係統........................................ ............................................................... (19)
第二節 機電運輸管理................................................................................................ (21)
第七章 其它掘進輔助係統........................................................................................ (24)
第八章 工程質量及文明生產標準............................................................................(27)
第一節 工程質量標準................................................................ ...............................(27)
第二節 文明施工標準................................................................................................(28)
第九章 巷道頂板管理....................................................................................... ........(30)
第一節 頂板管理........................................................................................................ (30)
第二節 掘進施工工程質量管理................................................................................ (30)
第三節 架棚安全措施...................................................................................... ........ (31)
第四節 巷道維修措施................................................................................................(31)
第五節 處理冒頂措施................................................................................................ (32)
第六節 斷層和破碎帶施工措施................................................................................ (32)
第十章 一通三防及安全管理.................................................................................... (34)
第一節 通風係統管理..................... ..........................................................................(34)
第二節 防瓦斯措施.................................................................................................... (34)
第三節 安全監測係統及管理................................................................................... (35)
第四節 綜合防塵措施................................................................................................ (35)
第五節 防滅火措施.................................................................................................... (36)
防煤層自燃發火措施.................................................................................... (36)
防治水措施.................................................................................................... (37)
第八節 爆破管理........................................................................................................ (38)
第九節 瓦斯就地排放措施........................................................................................ (40)
第十一章 規章製度............................................. .......................................................... (42)
第一節 交接班製度.................................................................................................... (42)
第二節 工程質量驗收製度........................................................................................ (42)
第三節 巷道維修製度................................................................................................ (42)
第四節 通風安全儀表使用檢修製度........................................................................ (43)
文明生產區域管理責任製........................................................................... (43)
第六節 安全隱患排查製度........................................................................................ (43)
第七節 煤質管理........................................................................................................ (43)
第八節 搶險專用物料的規定要求............................................................................ (44)
第九節 其它............................................................................................................... (44)
第十二章 安全避災路線..................................................................................................(45)
第十三章 事故案例..........................................................................................................(46)
第一章 工 程 概 況
序號 項 目 內 容 說 明
1 巷道布置 平麵圖見附圖一
2 工期要求 預計2012年3月1日開工,2012年6月15日竣工
3 巷道用途 12030采麵運輸
4 服務年限 約1年
5 工程量(m) 總工程量為752m
6 工程投資 預計工程投資266萬
7 工程結構
特 點
該麵井下位於先鋒煤業主井北翼,北鄰原西F10斷層,南臨原大橋煤礦采空區。
8 巷道標高 井上標高: +284.33~+285m
井下標高: +125~+108m
第二章 地質情況概述
序號 項 目 內 容 說 明
1 地質綜合柱狀圖 見附圖
2 頂
底
板
岩
性
描
述 頂板岩性 直接頂:厚度4~17m,平均10.5m,白色粗粒砂岩及中粒砂岩,中間含有雲母碎屑,局部較破碎,厚度係數2~4級
底板岩性 直接底厚度0~2m,硬度係數1~2級,黑色頁岩或炭質泥岩。向下為厚0~11m的深灰色中粒砂岩及砂質泥岩互層,硬度係數為2~4級,含有硫鐵礦結核,為二1煤層底板標誌層。
巷道所處層位 主體巷道處於二1煤中,煤層為黑色碎粒狀,從鑽孔情況來分析,該巷道所處的煤層厚度為2.2-4.5m。
3 煤
層
賦
存
條
件 采麵瓦斯情況 據豫工信煤【2010】200號,河南先鋒煤業有限公司瓦斯相對湧出量3.7m3/t,絕對湧出量1.27m3/min,為低瓦斯礦井。
突出危險性 煤層無突出危險性。
煤塵 粉末狀,屬於自燃煤層,自燃發火期為13個月。煤塵具有爆炸性,施工中加強煤塵管理。
地質構造 根據實揭地質和鑽孔成果及二1煤層底板等高線形態分析:該工作麵位於王英溝背斜西北部西側,地層一般傾向西,傾角19°左右,斷裂構造發育產狀變化不大。由於受采動影響,煤層頂板起伏變化較大,造成二1煤層厚度變化較大,大部分地段多為半煤岩,回采過程中將造成灰分增加,對正常回采及煤質管理產生較大影響。
水文地質 根據11020采麵掌握的水文地質資料分析,區域內頂底板含水量較弱,預計底板水對工作麵施工構不成威脅,但原電力礦老空水和老窯水嚴重威脅該工作麵掘進,必須堅持“有疑必探、先探後掘”的原則。
第三章 巷道支護說明書
第一節 巷道壓力情況
巷道沿二1煤層底板施工,頂、底和煤層按酥軟層位管理,在施工過程中應加強頂板管理,防止空頂漏頂和其它意外事故發生。
第二節 支護形式
一、支護形式:
巷道采用11#工字鋼梯形支護。
二、支護規格及選用材料說明:
巷道掘進全部使用11#工字鋼支護,淨巷道尺寸:上寬2.36m,下寬3.56m,中高2.324m,棚距0.4m,每棚18根板皮(幫6頂6),均勻布置。嚴格按質量標準化進行施工,搞好工程質量,隨掘隨支,正確使用好超前支護,做到一次成巷,嚴禁空頂作業。空頂空幫及時刹實背牢。
第三節 巷道支護斷麵圖及各種管線設備吊掛布置圖
(見附圖)
第四節 巷道支護特征及每米巷道支護材料消耗量
巷道
特征 巷道開口標高(m) +125m
巷道終點標高(m) +108m
巷道所處岩層層位及岩性 主體巷道在二1煤層中
掘進斷麵(m2) 小S毛=8.49m2 大S毛=8.69m2
淨斷麵(m2) 小S淨=6.68m2 大 S淨=6.88m2
每米支架數 2.5架/米
每米
巷道
材料
消耗
量 名稱 規格 單位 數量
梁 2600mm 根 2.5
腿 2600mm 根 5
供水管 4寸 米 1
排水管 4寸 米 1
風筒 Φ600mm 米 1
電纜 S16~35mm2 米 1
背木 10×10×50mm 塊 32
金屬網 500×600mm 片 9
風管 2寸 米 1
電話線 米 1
施工方法及勞動組織
第一節 施工方法
施工順序 施工順序為:現場交接班→安全檢查→沿中線→打眼→裝藥→聯線→灑水→打開噴霧→放炮→移前探梁→挑幫頂→出煤→支護,其中部分工序平行作業如:灑水、出煤、支護等。
施工方法 該工作麵采用人工裝運料、放炮掘進、煤電鑽打眼、人工架棚。
運輸方式 出煤 12030機巷→溜煤眼→主斜井→地麵
運料 平地料場→副井→12030機巷
施工工序
打眼→裝藥→放炮→移前探梁→挑幫頂→出煤→支護
工作製度 采用“三八”製工作製度
第二節 爆破說明書
1、爆破條件
瓦斯等級 低沼 鑽眼工具 煤電鑽
掘進斷麵 7.36m2 炸藥種類 煤礦許用三級
水膠炸藥
煤岩性 煤 雷管類別 Ms延期
電雷管
2、炮眼布置圖
巷道掘進炮眼布置圖 附圖
3、機巷掘進炮眼布置及裝藥量
巷道掘進炮眼布置及裝藥量表
眼號 炮眼名稱 眼
數 眼深
(m) 眼距
(m) 裝藥量 角度(°) 爆破
順序 聯線方式
kg/眼 小計(kg) 水平 垂直
1-4 掏槽眼 4 1.4 0.8 0.45 1.8 70 -20 1 串聯
5-6 底眼 2 1.2 0.9 0.45 0.9 70 -10 2 串聯
8-12 周邊眼 5 1.2 0.8 0.375 1.875 70 0-10 3 串聯
7 二圈眼 1 1.2 0.8 0.375 0.375 0 0 3 串聯
合 計 12 4.95
四、技術經濟指標
掘進巷道技術經濟指標表
序號 項 目 單位 數 量 備 注
1 掘進斷麵 ㎡ 8.69
2 淨斷麵 ㎡ 6.88
3 炮眼深度 m 1.0~1.4
4 炮眼個數 個 12
5 煤岩硬度 度 2~4
6 工作麵瓦斯情況 低瓦斯
7 雷管個數 個 12
8 裝藥量 kg 4.95
9 掘進工程量 m 752
10 切眼 m 120
第三節 勞動組織表
|